Activity Group Dates ----------------------------------------------------------------------------------------------------------- 1. Vent, disconnect services, cables, beam pipes... DRAGON Feb 18-22 2. Flush, isolate and disconnect DRAGON gas supply Detector Fac. (Openshaw/Goyette) Feb 21-22 3. Disconnect 1-2 electrical conduits Electrical Feb 21-22 4. Detach stands, reposition, align, re-grout Beamlines Feb 25-Mar 10 5. Extend conduits, reattach to stands Electrical Mar 11-12 6. Re-route gas lines Detector Fac. (Openshaw/Goyette) Mar 12-14 7. Connect services/Controls modifications DRAGON/Controls Mar 17-21 8. Vacuum test DRAGON Mar 20-21 9. Wire and assemble MCP2 DRAGON/Det. Fac. (Sheffer?) Mar 10-14* 10. Install MCPs, Vacuum & noise test DRAGON April 1